MoG changes are to be implemented cooperatively and in a timely manner.

The Government (Cabinet or Prime Minister) may specify a date by which a MoG change is to be completed (the completion date).

However, if the Government (Cabinet or Prime Minister) does not specify a completion date, entities are expected to complete MoG changes within 13 weeks from the MoG change date of effect (the commencement date).

Agency heads/accountable authorities involved in the MoG change are responsible for meeting this deadline and for implementing MoG changes in accordance with the principles outlined in this Guide and other relevant guidance.

The Department of the Prime Minister and Cabinet (PM&C), the Department of Finance (Finance) and the Australian Public Service Commission (APSC) will set milestones for the completion of large and/or complex MoG changes affecting many entities, as appropriate, to assist entities with their planning.

Entities and their agency heads/accountable authorities are responsible for managing the completion of MoG changes, and for negotiating and resolving contested issues.

It is good practice to complete a thorough due diligence exercise within the first 5 to 10 days to identify complex or contested issues early.

See Due Diligence and Change Management for more information.

Entities are encouraged to appoint an independent adviser early in the process to manage the information exchange process, facilitate negotiations and to help resolve contested issues. An independent adviser must be appointed if milestones are not being met. If it is apparent that a MoG change is large, complex, contested or there is likely to be a conflict of interest, an independent adviser should be appointed to identify potentially contentious issues and mediate a resolution.

The prompt sharing of all relevant information between entities to inform negotiations and the due diligence process is paramount to a prompt and effective MoG change implementation. Entities must notify all relevant parties of any delays in information sharing or process steps to maintain high levels of transparency.

A risk management approach will be required to avoid letting relatively minor issues delay negotiations.