National Security Office Precinct
On this page
The Department of Finance is leading the development of a National Security Office Precinct at York Park in Barton, ACT.
The precinct will deliver long-term secure office space for national security and other Commonwealth entities.
Location
Link copiedThe site, located at Block 5, Section 1 in Barton, is owned by the Commonwealth and was previously used as a temporary car park. It is bordered by Brisbane Avenue, State Circle, the York Park Oak Plantation and Windsor Walk.
The site was identified as a suitable location for the new precinct in consultation with the National Capital Authority.
Tenants
Link copiedThe precinct will include both public and private tenants and is expected to house up to 5,000 workers. Entities include the Office of National Intelligence and parts of the Department of Foreign Affairs and Trade.
Hospitality and retail services will be available for both workers and the public.
John Gorton Campus Car Park
Link copiedAs part of the project, the John Gorton Campus Car Park was built next to the John Gorton Building in Parkes, ACT.
It provides more than 1,000 spaces in the multi-level structure to support workers and visitors in the area.
The car park supports the goals of the John Gorton Campus under the National Capital Plan. It will also include a childcare centre and electric vehicle charging stations. For more information about parking and fees, read the fact sheet.
Appointed contractors
Link copied- Barpa, a majority Indigenous owned company, was engaged to design and construct the car park.
- Lendlease was engaged to deliver the precinct.
Project staging
Link copiedTo reduce disruption, the development has been staged.
Stage 1 - John Gorton Campus Car Park
- Construction started on 17 July 2023, and the car park opened on 12 February 2025.
- EV charger installation works and concrete facade elements will continue in 2026.
Stage 2 - National Security Office Precinct
- Early site works started in late 2024. Windsor Walk and York Park car parks were closed in stages from January 2025, with the site closed permanently on 12 February 2025. Construction is underway. For the latest information, read the project updates.
Costs
Link copiedThe overall project costs for the precinct are not published due to commercial and national security sensitivities.
The contracted value for the John Gorton Campus Car Park is $82.7 million (including GST). Details of this procurement are published on AusTender.
Sustainability targets
Link copied- Finance aims to deliver a precinct that demonstrates high standards in sustainable design throughout the asset’s lifecycle.
- The project is being developed in line with relevant environmental and sustainability requirements.
- The project will include provision for EV charging stations.
- The car park has been developed using recyclable materials and an open façade to promote natural ventilation.
Environmental impacts
Link copied- To meet environmental needs, Finance submitted a referral for the John Gorton Campus Car Park to the Department of Climate Change, Energy, the Environment and Water.
- The referral (EBPC 2022/09400) was approved with conditions on 27 April 2023. Details are available on the EPBC Act Public Portal.
- The future development of the precinct will not affect the York Park Oak Tree Plantation, which is included on the Commonwealth Heritage List.
Contractor and supplier opportunities
Link copiedLendlease is engaging construction companies and trade services to deliver the project. To find out about potential opportunities, email NSOP@lendlease.com.
More information
Link copiedFor the latest information, read the project updates.
To receive updates and newsletters about the project, subscribe to the NSOP mailing list.
Media releases
Link copied- National Security Office Precinct sod turn to celebrate construction commencement - 05 March 2025.
- First stage of National Security Office Precinct Project underway - 08 August 2023.
- Barpa awarded first significant Parliamentary Triangle construction project in two decades - Barpa | An Indigenous Construction Solution - 01 June 2023.
- Contract awarded to deliver the John Gorton Campus Car Park | Finance Minister - 25 May 2023.
- Contract awarded to deliver the National Security Office Precinct in Barton | Finance Minister - 27 March 2023.
Contact
Link copiedFor questions, email nsop.enquiries@finance.gov.au.