National Security Office Precinct project updates
On this page
The National Security Office Precinct (NSOP) project aims to deliver long-term secure office space for national security and Commonwealth entities.
This page provides regular updates on the project's progress, including key milestones, construction activities and upcoming changes.
Read more about the project.
2026 updates
Link copiedOctober 2026 - Updates to JGC car park facade panel works
What’s happening?
Fencing and foot path closures are occurring:
- From 2 November 2026 to end of March 2027 – a portion of the foot path to the north and sought of the JGC car park will be closed off. There’ll be an alternate path for use.
- You’ll see fencing put up around the north side of the JGC car park. This is to prepare the area for façade panel installation on the north side.
Figure 1 JGC car park façade panel works closure map
The south on-grade car park was closed on 26 October 2026.
Starting mid-November 2026, you’ll start seeing traffic management for King Edward Terrace, Parks. We’ll send more information out before that time.
Please note, dates and details of work are subject to change.
Contact the NSOP team via email at NSOP.enquires@finance.gov.au.
Works to bring the new Electric Vehicle (EV) charging stations at the John Gorton Campus Car Park into operation are continuing.
The project is expected to be completed shortly. Further information will be provided once they are ready for use.
2025 updates
Link copiedPower outage to the John Gorton Campus Car Park
Works on the installation of electric vehicle charging stations at the John Gorton Campus Car Park are ongoing. See below details of works occurring this week on Friday 28 November 2025 that will result in a short power outage (outside of office hours).
Works: Electric vehicle charging installation works will take place on the ground floor. Lifts and lighting will be temporarily out of service during this time.
Date/Time: 6pm to 7pm on Friday 28 November 2025 (outside of office hours).
Action: All users must vacate the car park by 5:30pm on Friday 28 November 2025, to ensure smooth exit and to minimise disruptions. While access to the exit will be maintained, we recommend exiting earlier to avoid potential impacts.
Contacts:
- Project Manager, Jones Lang LaSalle
- Department of Finance - NSOP.enquiries@finance.gov.au
Further details on the use of EV charging spaces will be shared once installation is complete.
Electric vehicle chargers coming to the John Gorton Campus Car Park
Works on the installation of 16 electric vehicle (EV) chargers will begin at the John Gorton Campus Car Park, Parkes ACT from Monday 24 November 2025. Works are expected to be completed by mid-December 2025, with chargers to be located on the ground floor.
Note:
- Accessible parking bays on the ground floor will not be affected.
- Only designated EV charging bays on the ground floor will be impacted.
- Electrical works will be done outside regular business hours to minimise disruption.
- No major disruptions to traffic flow are anticipated.
More details on the use of EV charging spaces will be shared once installation is complete.
The National Capital Authority (NCA) manages pay parking arrangements for the car park, further details on parking fees are available on the NCA website.
Kings Avenue and Brisbane Avenue traffic movement impacts
There will be impacts to traffic movements on Kings Avenue and Brisbane Avenue in October 2025 due to the continuing construction works at the National Security Office Precinct Project site at York Park Barton, ACT - Block 5, Section 1.
The schedule of works and impacts are listed below:
From 13 October 2025
Potential impact: Traffic movements change with the main entrance to the site via Kings Avenue and site traffic exiting via Brisbane Avenue.
Works description and impact: Trucks will now enter the site gate on Kings Avenue and exit via the gate on Brisbane Avenue, Barton ACT.
From 20 to 24 October 2025
Potential impact: Trucks will now enter the site gate on Kings Avenue and exit via the gate on Brisbane Avenue, Barton ACT.
Works description and impact: Lane closure to enable crane set up to lift sheds onto Windsor Walk.
Road and travel impacts
As construction continues there may be additional travel impacts. The latest information about road and travel impacts in the Barton area, can be found on the ACT Government’s website and from the National Capital Authority’s website.
Travel Impacts - Built for CBR - ACT Government
Road closures - City Services - ACT Government
Closure - National Capital Authority
National Security Office Precinct construction
Construction works are continuing to progress on the National Security Office Precinct project. The precinct is being developed at York Park (Block 5, Section 1), a prominent Commonwealth owned site within Barton, previously used as a temporary car park.
Road and travel impacts
As construction continues there may be travel impacts. The latest information about road and travel impacts in the Barton area, can be found on the ACT Government’s website and from the National Capital Authority’s website.
Travel Impacts - Built for CBR - ACT Government
Road closures - City Services - ACT Government
Closure - National Capital Authority
Partial closure: John Gorton Campus Car Park between 18 July 2025 to 21 July 2025
The John Gorton Campus Car Park will be partially closed for rectification works from 6pm Friday 18 July 2025 to 4am Monday 21 July 2025. Roadside signage has been installed on Kings Avenue.
During this period, access to car parking on levels 1-4 will be unavailable. The ground floor will remain open.
Please ensure all vehicles have been removed from the John Gorton Campus Car Park by 6pm Friday 18 July 2025.
National Security Office Precinct construction
Works are progressing on the construction of the National Security Office Precinct project, which is being developed at York Park (Block 5, Section 1), a prominent Commonwealth owned site within Barton, previously used as a temporary car park.
Service diversion works and road impacts
As part of the construction of the precinct, service diversion works are being undertaken and will impact surrounding roads, including Brisbane Avenue and Kings Avenue.
The latest information and news about traffic impacts can be found on the ACT Government’s website and from the National Capital Authority’s website.
Travel Impacts - Built for CBR - ACT Government
Road closures - City Services - ACT Government
Closure - National Capital Authority
John Gorton Campus Car Park
The John Gorton Campus Car Park opened on 12 February 2025 and is a multi-level public car park providing over 1,000 car spaces.
The John Gorton Campus Car Park was an enabling project for the development of the precinct, replacing the loss of car parking spaces from York Park and providing parking for local workforce and visitors to the area.
Further landscaping works and other completion activities around the John Gorton Campus Car Park will continue throughout 2025. This will include precast concrete elements of the northern and southern facades to be installed later this year and are not required for the safe operation of the car park.
Due to these works approximately 80 spaces across the car park will be offline until completion.
National Security Office Precinct construction
The John Gorton Campus Car Park, Parkes, ACT will be open and ready for use tomorrow morning, Wednesday 12 February 2025.
Parking will be no longer available at York Park Car Park, Barton, ACT (accessed via Brisbane Avenue) with the remaining southern section of the car park permanently closed from this evening.
John Gorton Campus Car Park
The John Gorton Campus Car Park is a multi-level public car park and provides over 1,000 car spaces.
How do I pay for parking?
Pay parking arrangements area managed by the National Capital Authority (NCA) using the EasyPark system. The cost of parking aligns with all other NCA managed parking which is currently $17.00 per day for long stay parking.
Pay parking ticket machines are located near the lifts or alternatively download the EasyPark app to pay (iphone via the App Store or Android via the Play Store).
How do I access the car park?
Access is via the signalised traffic light at the Kings Avenue and Blackall Street intersection (there are no boom gates on entry or exit).
What is the vehicle clearance height?
The vehicle clearance height of the car park is 2.2 metres.
More information is available in the John Gorton Campus Car Park fact sheet.
IMAGE
Alternative parking and transport options
There are alternative parking and transport options in the Parkes and Barton area. Users are encouraged to explore options, plan their trip and allow more travel time due to the car parking changes.
Reminder - opening of John Gorton Campus Car Park and permanent closure of York Park Car Park
The John Gorton Campus Car Park, Parkes ACT opens on Wednesday 12 February 2025, with the remaining southern section of the York Park Car Park, Barton ACT (accessed via Brisbane Avenue) to close permanently on the same day to facilitate development of the National Security Office Precinct project.
IMAGE
Access to John Gorton Campus Car Park
The John Gorton Campus Car Park fact sheet provides information about utilising the car park, which is accessed via the signalised traffic light at the Kings Avenue and Blackall Street intersection.
IMAGE
Alternative parking and transport options
Impacted users are encouraged explore alternative parking and transport options early and allow more time for travel over this time.
John Gorton Campus Car Park opening and York Park Car Park closure
The John Gorton Campus Car Park, Parkes ACT opens on Wednesday 12 February 2025 with York Park Car Park, Barton ACT full closure taking place on the same day.
York Park Car Park will close to facilitate the development of the National Security Office Precinct project.
The John Gorton Campus Car Park is an enabling project for the Precinct’s development and will:
- provide over 1,000 car spaces in Parkes, ACT for local workforce and visitors to the area
- replace the loss of car parking spaces from the closure of the York Park Car Park, Barton ACT
- offer accessible parking spaces and motorcycle bays
- EV charging stations to be available later in 2025.
Further landscaping works and other completion activities around the John Gorton Campus Car Park will continue throughout 2025. This will include precast concrete elements of the northern and southern facades to be installed later this year and are not required for the safe operation of the car park.
Due to these works approximately 120 spaces across the car park will be offline until completion.
The John Gorton Campus Car Park fact sheet provides information about utilising the car park.
IMAGE
As planned and notified below, the north section of the York Park Car Park (276 spaces) closed with no access to the site on Monday 13 January 2025.
Early works required for the closure of Windsor Walk have now been completed and the closure of Windsor Walk will take effect from Monday 20 January 2025.
An update will be provided shortly regarding the status of the John Gorton Campus Car Park opening and York Park Car Park full closure which is planned for the end of January 2025.
Key dates:
- Early work - commenced on site on 15 November 2024.
- 6 January 2025 - no major impacts to car parking. Fencing will be established to separate the southern section of the car park from the smaller northern section next to the York Park Oak plantation.
- 13 January 2025 - closure of the northern section of York Park (276 spaces) with no pedestrian or vehicle access from that date. Brisbane Avenue car parking remains available (440 spaces).
- 20 January 2025 - Closure of Windsor Walk (92 spaces) with no pedestrian or vehicle access from that date.
- End January 2025 - Access to the Brisbane Avenue car parking (440 spaces) will remain available to the public until the opening of the John Gorton Campus Car Park, forecast in late January 2025. Upon opening of the John Gorton Campus Car Park, access to the York Park Car Park will be permanently closed.
See the below update (7 January 2025) for site access and pedestrian maps.
Changes to York Park and Windsor Walk car parks
The York Park car park will remain partially open (access via Brisbane Avenue) until its full closure for major construction works, anticipated by late January 2025.
Increased site activity is expected throughout January 2025, which will impact some parking availability during the school holiday period. Staged closure of the York Park and Windsor Walk car parks will enable progression of works while keeping the majority of parking spaces open until the opening of the John Gorton Campus Car Park.
Impacted users are encouraged to monitor this webpage for the latest information, in addition to exploring alternative parking and transport options early and allow more time for travel - especially when returning in the new year.
The below table and map provide an overview of site access and parking closures expected in January 2025.
Key dates:
- Early work - commenced on site on 15 November 2024.
- 6 January 2025 - No major impacts to car parking. Fencing will be established to separate the southern section of the car park from the smaller northern section next to the York Park Oak plantation.
- 13 January 2025 - Closure of the northern section of York Park (276 spaces) and Windsor Walk (92 spaces), with no pedestrian or vehicle access from that date. Brisbane Avenue car parking remains available (440 spaces).
- End January 2025 - Access to the Brisbane Avenue car parking (440 spaces) will remain available to the public until the opening of the John Gorton Campus Car Park, forecast in late January 2025. Upon opening of the John Gorton Campus Car Park, access to the York Park Car Park will be permanently closed.
IMAGE
Pedestrian map following York Park Car Park closure
The below map shows an example of the pedestrian pathways that will be accessible around the York Park site from late January 2025.
IMAGE
John Gorton Campus Car Park
The final opening date and timing of access to parking is subject to conditional factors, such as inclement weather and final approvals.
Details of the opening date and arrangements will be shared with relevant agencies in advance and published on this webpage.
2024 updates
Link copiedChanges to York Park and Windsor Walk car parks
Early site works commenced along Windsor Walk on 15 November 2024. The York Park Car Park will remain open (access via Brisbane Avenue) until its full closure for major construction works, anticipated by late January 2025.
Increased site activity is expected throughout January 2025, which may impact some parking availability during the school holiday period. Details of any impacts will be shared in advance and published on the NSOP project website.
The below map provides an overview of site and parking access during December 2024 and the current Windsor Walk closure.
IMAGE
Pedestrian map following York Park Car Park closure
The below map shows pedestrian access around the York Park site from late January 2025.
IMAGE
John Gorton Campus Car Park
The John Gorton Campus Car Park is anticipated to open in late January 2025.
Finance is working with contractors to confirm the exact opening date and timing of access to parking onsite due to conditional factors, such as inclement weather and final approvals. Details of the opening date and arrangements will be shared with relevant agencies in advance and published on the NSOP project website.
Car park users are encouraged to check this webpage for the latest information on availability and opening dates Information will continue to be shared in advance once dates and details are confirmed.
The Department of Finance is leading the development of the National Security Office Precinct in Barton, ACT.
Lendlease is the managing contractor for the precinct and is expected to commence early works from November 2024, with full site closure from early 2025.
The project site area comprises the York Park Car Park and Windsor Walk in Barton ACT.
Upcoming changes
Early site works will commence along Windsor Walk from 15 November 2024. The York Park Car Park will remain open (access via Brisbane Avenue) until the site is permanently closed for major construction works which are anticipated to commence in early 2025.
Program summary:
- From 15 November 2024 to early 2025 - early works and impacts to car parking.
- From early 2025 - Construction works and permanent closure of car parks.
IMAGE
More information
The below fact sheets provide more information about car park access during the early works, parking options and travel options:
NSOP Project Car Park Access Overview - November 2024
NSOP Project Parking Options - November 2024
NSOP Project Travel Transport Options - November 2024.
Further information will be communicated as the project progresses.
John Gorton Campus Car Park
The development of the John Gorton Campus Car Park is expected to be completed and open to the public in early 2025. The John Gorton Campus Car Park will provide over 1,000 car spaces in a multi-level car park, within close vicinity for nearby workers.
for more information on the project, read the National Security Office Precinct project page.
More information
Link copiedFor more information about the precinct:
- subscribe to the NSOP Mailing List to receive updates
- email questions regarding the precinct to NSOP.enquiries@finance.gov.au
- read about the NSOP project.